@@ -12,121 +12,5 @@ export interface MetroStation {
image?: string;
}
export const metroStations: MetroStation[] = [
{
id: 1,
name: 'ABİDİN PAŞA',
status: 'completed',
progress: 100,
startDate: '10 Ocak 2023',
expectedCompletion: '30 Aralık 2023',
actualCompletion: '25 Aralık 2023',
connections: ['M1'],
features: ['Aktarma İstasyonu', 'Otopark', 'Engelsiz Erişim', 'Ticari Alanlar'],
dailyCapacity: '45,000'
},
{
id: 2,
name: 'AŞIK VEYSEL',
status: 'completed',
progress: 100,
startDate: '15 Şubat 2023',
expectedCompletion: '15 Mart 2024',
actualCompletion: '10 Mart 2024',
connections: [],
features: ['Modern Tasarım', 'Güvenlik Sistemleri', 'Engelsiz Erişim'],
dailyCapacity: '35,000'
},
{
id: 3,
name: 'TUZLUÇAYIR',
status: 'in-progress',
progress: 75,
startDate: '1 Mart 2024',
expectedCompletion: '30 Haziran 2025',
connections: [],
features: ['Modern Tasarım', 'Güneş Enerjisi', 'Güvenlik Sistemleri', 'Engelsiz Erişim'],
dailyCapacity: '40,000'
},
{
id: 4,
name: 'GENERAL ZEKİ DOĞAN',
status: 'in-progress',
progress: 45,
startDate: '15 Nisan 2024',
expectedCompletion: '30 Eylül 2025',
connections: [],
features: ['Otopark', 'Bisiklet Park Alanı', 'Güvenlik Sistemleri'],
dailyCapacity: '30,000'
},
{
id: 5,
name: 'FAHRİ KORUTÜRK',
status: 'planned',
progress: 15,
startDate: '1 Haziran 2024',
expectedCompletion: '31 Aralık 2025',
connections: [],
features: ['Modern Mimari', 'Yeşil Alan', 'Engelsiz Erişim'],
dailyCapacity: '35,000'
},
{
id: 6,
name: 'CENGİZHAN',
status: 'planned',
progress: 10,
startDate: '1 Ağustos 2024',
expectedCompletion: '28 Şubat 2026',
connections: [],
features: ['Ticari Alanlar', 'Otopark', 'Güvenlik Sistemleri'],
dailyCapacity: '32,000'
},
{
id: 7,
name: 'AKŞEMSETTİN',
status: 'planned',
progress: 5,
startDate: '1 Ekim 2024',
expectedCompletion: '30 Nisan 2026',
connections: [],
features: ['Modern Tasarım', 'Engelsiz Erişim', 'Bisiklet Park Alanı'],
dailyCapacity: '28,000'
},
{
id: 8,
name: 'NATOYOLU',
status: 'planned',
progress: 5,
startDate: '1 Aralık 2024',
expectedCompletion: '30 Haziran 2026',
connections: ['M2'],
features: ['Aktarma İstasyonu', 'Otopark', 'Ticari Alanlar', 'Modern Tasarım'],
dailyCapacity: '50,000'
}
];
export const getStatusColor = (status: MetroStation['status']) => {
switch (status) {
case 'completed':
return 'bg-green-500';
case 'in-progress':
return 'bg-blue-500';
case 'planned':
return 'bg-yellow-500';
default:
return 'bg-gray-500';
}
};
export const getStatusText = (status: MetroStation['status']) => {
switch (status) {
case 'completed':
return 'Tamamlandı';
case 'in-progress':
return 'Devam Ediyor';
case 'planned':
return 'Planlanıyor';
default:
return 'Bilinmiyor';
}
};
// Mock data removed - all data comes from database
export const metroStations: MetroStation[] = [];